Summer 2001

Signature of a Control Management Contract
with an undisclosed Global Bank.

I will be in charge of overseeing, changing,
controlling and releasing different management processes.
More information


PROJECT FINANCING INFRASTRUCTURES
An Analysis realized by György CSIZMADIA

MBA, Instituto de Empresa, Spain.

Madrid, July 1998

 

Disclaimer : The objective of this paper is NOT to give legal or financial advices.
This article was NOT endorsed by the Firms and Institutions which helped me logistically. It just expresses my views on this issue. If you were considering action you should seek your own professional advice.


INDEX


Definition


Five Main Characteristics of Project Finance
The non-burdening of the balance Sheets?
Advantages and Desadvantages of Project Finance
The parties in  presence in a Project Finance Deal



Three Different phases in Risk  Coverage and how to assess them.

1. Pre-Completion risk

1) Sponsor risk
2) The Political or Authorization Risk

2. Construction Phase: Period of the Highest Risk
1) Risk of a total write-off
2) Technology Risk

3. The Operation Phase
1) The employment by the sponsor of a third-party operations and maintenance contractor
2) The distribution of the revenue stream

3) The Input and Supply Risks have to be considered

4) Concession Agreement

5) Offtake contracts


Financial Design of the Operation

1. External Financing

2. Equity Commitment of the Sponsors

3. The inherent conflict between the sponsors and the external financiers

1) Return
2) Security
4. Allocating risk between the project sponsors and the financiers



References

 

 

DEFINITION

Back to Index

Project Finance is a technique, which can permit enterprises (Project Finance for the private sector), and governmental entities to finance significant infrastructures that require such large amounts of capital that they would strain the ability of these entities to raise sufficient equity.

The lender will look primarily to the revenue stream created by the project for repayment, at least once operations have commenced, and to the assets of the project (including contracts for the supply of raw materials, the sale of the finished product and a host of other arrangements relating to the continuing operation) as collateral for the loan. 

That is not to say that project financing is inherently risky for debt providers. Project finance requires the parties to reconsider the positions that they would typically adopt in a financing transaction and give detailed consideration to the overall viability of the project itself. Debt and equity providers need to ensure that risks are identified and covered, and any residual risks are properly allocated so as to provide adequate incentives to prevent opportunism and to ensure that all parties are committed to the success of the project.

It should be noted in this era of privatization and deregulation that PPP (i.e. public-private-partnership) has become fashionable. 

Another objective of Project Finance would be to obtain the needed infrastructure today, without burdening the balance sheets. I will comment this assumption below.
 

Five Main Characteristics of Project Finance.

Back to Index

  1. The project is perfectly identifiable and distinct from the other projects and activities of the sponsors.
  2. Project Finance is only, also in theory, financed on the future cash flows stemming from the project and without the guarantee of the sponsors. It works, therefore when the stream of future income is sufficient to make the project profitable.
  3. In theory the financing should be designed according to the forecasted cash flows and not according to the different guarantees in place.
  4. Project Finance deals with extremely high level of indebtedness. Obviously leverage is benefic but also increases the financial risk.
  5. In Spain it is used in long-term capital intensive project: 2.000 millions ESP (€ 12.500.000) seems to be the bottom line due to the costs of the legal and financial engineering.


The non-burdening of the balance Sheets?

Back to Index

The non-burdening of the balance sheets is very theoretical. The seventh council directive of the European Union of 13 June 1983 based on the Article 54 (3) (g) of the Treaty on consolidated accounts (83/349/EEC) requires a consolidation of all the activities independently from their mode of financing. 

Consolidated accounts and a consolidated annual report will be required if a parent undertaking: 

  • has a majority of the shareholders' or members' voting rights in another undertaking (a subsidiary undertaking); or
  • has the right to appoint or remove a majority of the members of the administrative, management or supervisory body of another undertaking (a subsidiary undertaking), and is at the same time a shareholder in or member of that undertaking; or 

  •  
  • has the right to exercise a dominant influence over an undertaking (a subsidiary undertaking) of which it is a shareholder or member, pursuant to a contract entered into with that undertaking or to a provision in its memorandum or articles of association, where the law governing that subsidiary undertaking permits its being subject to such contracts or provisions. A Member State need not prescribe that a parent undertaking must be a shareholder in or member of its subsidiary undertaking. Those Member States, the laws of which do not provide for such contracts or clauses shall not be required to apply this provision; or
  • is a shareholder in or member of an undertaking , and:
  • a majority of the members of the administrative, management or supervisory bodies of that undertaking (a subsidiary undertaking) who have held office during the financial year, during the preceding financial year and up to the time when the consolidated accounts are drawn up, have been appointed solely as a result of the exercise of its voting rights; or 
  • controls alone, pursuant to an agreement with other shareholders in or members of that undertaking (a subsidiary undertaking), a majority of shareholders' or members' voting rights in that undertaking. 
In other words Project Finance activities might end up in the balance sheets of the sponsors in function of their percentage of participation in the capital and in the management of the project.
 

Advantages and Desadvantages of Project Finance.

Back to Index

ADVANTAGES:

For the sponsors: 

    • Avoids having the project debt reflected on their balance sheets (to be mitigated as mentioned in the definition).
    • Should avoid covenants (highly unrealistic before completion). 
    • Useful when the sponsors creditworthiness or borrowing capacity is less than adequate.
    • Useful when the risk inherent to the project overtakes the risk the shareholders are ready to assume or when they want to diversify the risk.
    • It is fine when clients exist and are already satisfied with the project.
DESADVANTAGES:

Due to its nature Project Finance is lawyer-intensive: the financing of the project will be determined essentially by the adequacy of the security package (which also implies the participation of external technical consultants).


The security package means:



1. Availability of sufficient financial support by or recourse to creditworthy entities to:
    • Cover all costs.
    • Guarantee the timely completion of the project.
    • Satisfy stipulated performance guarantees.


    2. And availability of a reliable source of project revenue to:
     

    • Cover operating costs.
    • Cover debt service.
    • Cover a reasonable return to the sponsors.


    3. Mechanism insuring the timely availability and correct allocation of the project revenue to service debt and cover operating costs. 

    Two big concerns are in presence: the revenue stream and the currency risks. The revenue stream risk exists especially in project such as roads or bridges which don´t lend themselves to user contracts and a steady dependable revenue stream. Details on the revenue stream and the currency risks can be found in the Offtake Section of this paper).
     


PARTIES IN PRESENCE, BESIDES THE BANK, IN A PROJECT FINANCE DEAL.

Back to Index

1. The sponsors may be either one company or a consortium of parties interested in the project, for example contractors, suppliers or users of the product to be produced by the project. 
    It is likely that the project sponsors will set up a Single Purpose Company to build and operate the project in order to isolate them from any project risks additional to the capital they have invested.

    2. The bankruptcy remote Single Purpose Company created to frame the project. 

    Bankruptcy Remoteness means that the entity will have to be non-trading and liability-free. Moreover, the Single Purpose Company´s activities will be restricted only to those essentials to the relevant project.

    The project sponsors own the shares of the Single Purpose Company and it would be this entity which would likely be the borrower. The reason is that sponsors do not want the funding of the project to restrict their ordinary business activities through ongoing recourse post completion (which would have a balance sheet impact as well as binding the sponsors to ongoing obligations, including restrictive covenants).

    3. The external consultants i.e. lawyers, technical experts, public relations firms, …

    4. Supranational, Governmental and Regional Authorities acting in three different ways:
     

    • They will deliver administrative authorizations.
    • They might be interested in project financing public infrastructure (PPP) or in becoming customer of an infrastructure.
    • They could bring in funds or give their aval.


    5. Insurance companies since they evaluate the risks and their extents.

    6. The constructors and operators.

The different roles of the Bank and the degree of sophistication involved will usually be driven by the size of the project.
1. Lender: the bank can loan money to the sponsor or to the Single Purpose Company.
    2. Syndicator of loans to other lenders: to spread the risks across a number of lenders.

    3. Guarantor: it is an effective mechanism to induce other commercial banks to participate in the project funding.

    4. Underwriter agreement to indemnify parties for a loss incurred by non-performance of the project.

    5. Equity Investor: the bank invests risk capital for which the Single Purpose Company has no obligation of repayment in terms of principal and interest. It seems therefore fair to secure the payment of preferred dividends.

    6. Financial and Investment Advisor acting in three fields:
     

  • Economic Viability Analysis i.e. definition of the objectives and formalization of the information into a structured business plan.
  • Financial Engineering and Risk Coverage. 
This implies the design of an optimized financial structure via the identification of the different options of financing and of their financial risks. The proposal of contracts mitigating the identified risks is obviously included in the Financial Engineering task.
  • Evaluation of the Contractors and Providers.
A system of selection and control must be implemented and applied with an active advising role in the contract negotiation processes.




Three Different Phases in Risk Coverage and how to assess them.

Back to Index


1. Pre-Completion Risk.

Back to Index

Pre-completion risk means the risk stemming from the project until completion. It is obvious, and if not obvious at least safe, that an external recourse (i.e. not only a recourse limited to the project itself) will have to be secured.

The first step in allocating pre-completion risk is to define what is meant by completion. 

The bank and the sponsors will have to agree on the point at which the project is complete and accordingly when money must start being repaid. This will need to be a point in time which can be judged from an objective basis as the sponsors may be keen to delay the point at which repayments must start, while the lenders will be anxious that this point occurs as early as possible in the construction process to avoid the loss of potential revenues. 

Completion is usually defined to include the project producing at a minimum rate. That rate will usually relate to the minimum level of production required under take-or-pay or similar contracts. 

A guarantee from third parties such as insurance against physical damages, consequential loss and third party and public liabilities will have to be required from the sponsor.

The pre-completion risk includes the sponsor risk and also the risk for the sponsor of not obtaining the necessary regulatory approvals to begin the project.


Sponsor risk.

It is very important to assess it adequately since in general it is associated with completion risk.

Sponsor risk can be broken down into two elements:

1. Equity commitment.
    It seems to be normal for a bank to require a contribution of anything from 15 to 50 % of the project cost to ensure the sponsor´s continued commitment.

    In terms of risk sharing, the best interest of the Bank is to see that entities with direct experience of the business are willing to risk their money in support of the project as a worthwhile venture. The same comment applies regarding the participation of other financing entities.

    The subordinated debt guaranteed by the shareholders as well as the subsidies obtained by the project are considered as equity commitment.

    2. Corporate strength and experience.

    Regarding corporate substance, it is obvious that it is preferable to work with corporate sponsors with substantial technical expertise and financial depth.

     
    In order for the bank to assess the risks connected with the implementation of the project, the sponsor should be required to describe the arrangements for implementation, which includes a description of the major components of the project. 

    The description of the major components includes a summary of the major features, terms and conditions of the contracts with the contractors in charge of implementation, the name of the contractor in charge of each component and the reasons for selecting the particular contractor and its relevant track record.

    The track record of the contractor is important because it qualifies the contractor in terms of its experience in work of a similar kind (related with the technology risk).

    Dates and types of contracts in which the contractor was previously engaged would be important.


 
The Political or Authorization Risk.
Back to Index

It is important for the bank to be protected against the consequences of a project breaching official consents and guidelines, especially in the environmental field. 

  • The Project Company must be authorized to construct and operate the project and must have any necessary concessions, licenses and approvals.
This sounds obvious and in practice it means that full details of all consents and approvals, planning, environmental, generating license, etc.... (national, regional and municipal), which are expected to be required and the status of the efforts being made to obtain such consents will have to be presented to the bank.

Although the lenders´security over the project assets and contracts may give them the ability to step in and take control of the project in the event of a default, any radical measures such as the sale of the project company or replacement of the management of the project company may require governmental approval. To apprehend this possibility, an analysis of the ability of the project to meet likely future constraints and limits will also be provided to the bank. 

A concern in addressing the political risk is the possibility of a change of government leading to a change in law or in the regulatory regime that could interfere with the project. 

The most extreme form of political risk would be expropriation, which sounds extremely remote in Spain.

  • Regarding the environmental risk, due to the increasingly demanding and restrictive legislation controlling the impact of industry on the environment, the costs of failing to comply with such legislation can be significant. 
Environmental liabilities will attach primarily to the project operators but can also attach to the project sponsors and lenders. Since the liabilities for environmental damages can be extensive and ruin a project's profitability the Single Purpose Company shall perform an environmental assessment. 

Moreover the bank will seek to shield the borrowing vehicle from such liabilities by ensuring there is a responsible, creditworthy independent operator who is responsible for managing such risks.
 


2. Construction Phase: period of the highest risk.

Back to Index

Risk of a total write-off in respect of a project that never produces cash flow.
Back to Index

The risks exist in:

  • Delay in Completion.
  • Abandonment.
  • Cost overruns.
  • Failure to achieve stipulated performance levels.
The construction contractors and the sponsors should assume those risks.

For the construction contractors: 

  • Importance of lump sum turnkey contracts with guarantees of completion and performance with damages payable if such guarantees are not met. Clauses are inserted in the contractors´s agreements obliging them to complete the construction and start-up of the project without regard to any limitation on liability under the construction contract, and to pay liquidated damages up to 40 % of the contract price if the project was not completed on time and to specified performance levels.
  • Back-stopping devices (adequate insurance package, surety bonds, bank guarantees or letter of credit issued by reputable institutions) in case of abandonment, default or other similar occurrences threatening the timely and successful completion of the project. A cession of the benefits of the different back-stopping devices will be inserted in favor of the Single Purpose Company or preferably directly to the Bank.
For the sponsors:

Since no contractor will assume project risk beyond those normally associated with the construction activities under the turnkey contract, the sponsor will be expected to undertake all other pre-completion risks. Nevertheless the risks are sometimes shared between the sponsors and the lenders.

  • Cost overrun commitment to cover the possibility of increased costs outside the contractor ´s scope of work (a description and justification of any cost contingency is expected). 
Equity and Debt Subscription: In the event of a cost overrun or delay both the financiers and the sponsors agree to provide further funding. This may be on a pro-rata basis or in alternative tranches. The financiers may insist on a cap on further funding which they are committed to provide. 
Stand-by Facility: The parties may put in place contingent underwriting type facilities to cover overruns. These facilities may be provided by the project sponsors or related companies. 

Overrun Undertaking: The sponsors agree to provide the overrun amounts above the pre-agreed debt and equity amounts. These may be required to be paid by way of additional capital as cost occurrences are identified during the construction phase. 

Insurance: The project sponsor or the borrowing entity may be required to take out insurance against construction delays or cost overruns.

  • In case of delay, responsibility for any costs necessary to insure the completion of the project that is not covered by the contract. This can be materialized under the form of a Completion Guarantee where the project sponsors agree to repay the loan either in full or on the basis of an agreed repayment schedule if the project is not completed on time. 
Completion Undertaking is another method: the sponsors agree to contribute any additional moneys that are required in order to ensure that the project reaches the agreed completion stage.

If the delay affects the overall long-term economic viability of the project the sponsor may remain liable under the completion guarantee or may be required to "top up" the cash flow if, or for as long as, it proves insufficient to cover debt service and operating costs.

  • Underwriting of the loan obligation by the sponsors prior to the commencement of operation at a specified level. The reason is that the primary source of repayment of the loan is the project cash flow, therefore the underwriting is a form of completion guarantee.
  • Letter of Credit: the project sponsor may be required to obtain a letter of credit or guarantee from a bank.

    Technology Risk
Back to Index

This is normally seen as a sponsor risk. It is important for the bank to be in presence of a predictable process (particularly with power plants); a study of feasibility will be required and the opinion of an independent technical consultant might also be useful.

Detailed examination demonstrating that:

  • The technology has a satisfactory track record (a completion test is also an option).
  • The contractors involved in the project as well as the suppliers have experience of the technology.
  • The guarantees and warranties are adequate.
  • Maintenance and component replacement are easy.
  • The availability and efficiency levels predicted can be easily achieved.



3. The Operation Phase.

Back to Index

Operation risk is the risk to the forecasted cash flow arising from the failure of operations of the project. 

  • The employment by the sponsor of a third-party operations and maintenance contractor is an element of security due to the deeper reserves of skills and personnel which this can make available to a project and also because the costs can be contractually fixed. Operative leasing is a similar option.
Back to Index
    The operators will be chosen like all the contractors. They should be experienced and recognized in their field. The track record is important since it qualifies the operators in terms of experience in work of a similar kind.

    A definition of the incentives and penalties applicable to the achieved level and quality of the operations should be considered.
     

  • The distribution of the revenue stream.

Analysis of the market: Market description, location and size.

The survival and existence of a business in a market economy is wholly dependent on market demand. Thus a description of the customers´need and profile is expected as well as one of the market environment (competitors).

Another fundamental information is the one dealing with the factors affecting the growth of demand (financial position of the buyers and substitutes).

Again the quality of the operators will play an important role since as far as possible the bank will pass to third-party contractors the risk of reduced prices chargeable to the users. 

Analysis of the revenue stream: the Discounted Cash Flow Model.
Various types of costs have to be taken into consideration to screen adequately the cash flow assumptions and forecasts.
  • Capital costs of the project (initial investment).
Capital costs can be viewed as the investment from which long-term benefits are expected. The capital costs reside in the business for subsequent years with the view that such items will make a positive contribution for several years in the future.
Those capital costs will be accounted as an asset and depreciated over the subsequent years.
  • Operating Costs.
They include, not limitedly, maintenance, materials, labor, service utilities, storage, handling, etc.
The Input and Supply Risks have to be considered:

Back to Index

It includes the risks existing when the project depends upon a reliable source of supplies for its operation. 

Sometimes this is a hard thing to guarantee. An example would be the availability of wind energy for a wind power plant. In cases like that, a completion test might be valuable i.e. building one unit in the projected location before starting the construction of the entire chain of wind power plant.

In most case the supplies stem from human suppliers and then it will be mandatory to be in possession of a demonstration of the security of the supply arrangements.

The sponsor has to show that the assumptions made relating to the quantities and pricing are conservative and that even on this basis the proposed debt can be retired with a significant margin of safety.

Different scenarios are to be considered: 
  • Increase of the raw material prices and/or of the quantities necessary.
  • Problem in the availability of the adequate quantity of raw material at the planned price.
  • The quality of the raw material is also important.
  • Changes in the demand of the service or product and/or in the prices the customers are willing to pay.
The answers to those relatively common problems can consist in long-term purchase agreements and/or in use of derivatives.

Another technique for minimizing supply risk is the put-or-pay arrangement where the supplier is committed to supply a minimum quantity of raw material or to pay a fixed level of compensation to the project company.

Concession Agreement: the governmental assurances are particularly important.

In a toll road project, the cash flow is generated by the public use of the infrastructure and there is no long-term contractual arrangement with the users. 

There is however a long-term agreement of exclusive right to collect tolls generated by the use of the particular project (and perhaps a degree of exclusivity) between the government and the sponsor.

It is important to provide for a periodic adjustment to the stipulated toll rates in order to reflect inflation. In some cases the project sponsors assume the traffic risk while in others the traffic risk is assumed by the government.
 

  • Offtake contracts.
  • Offtake contracts have to be inserted in infrastructure projects. They prevent the offtake risk i.e. the risk that the project fails to generate adequate income.
    Components:
    1. Term at least co-terminous with the term of the loan agreement. A year or so of cushion appears to be a common practice.

    2.  
    3. Committed Contracts i.e. long-term sale contracts for the service and product offered and/or use of derivatives.


      In the case of a project such as a power generation plant producing a commodity for sale, the long-term contract with a reliable party for the purchase of the energy is called a "throughput agreement"

      That contract will usually stipulate not only a minimum quantity to be purchased but also guarantee a minimum level of revenue to the Project Company to enable the Project Company to service its debt.

      Projects such as roads where payback is from tolls cannot be protected to the same extent

      The "take or pay" clause is also an option, it implies that the buyer agrees to buy or pay a product or service in predetermined quantities and at a predetermined date. In case of non-compliance he will have to pay a penalty which can reach the amount of the portion of the contract. 
       

    1. Price insuring coverage of debt service, payment of operating costs and a reasonable return to the investor. 

    2. The linkage mechanism is another offtake clause; it links the price of the service or product offered to the different costs involved and their evolution. The price has to be adjustable to reflect any increase in variable operating costs and any decrease in the value of the local currency.

      A clause allowing for a price revision written or justified upon other terms is also possible.
       

    3. Swap contracts and similar hedging arrangements to reduce the Interest Rate and Foreign Exchange Risks.

    4. The Interest Rate Risk arises frequently where, for example, a project´s income stream may depend upon an implied fixed rate present value calculation and the coupon on the notes is floating rate. Additionally, the income stream may be denominated in a different currency from the Single Purpose Company´s debt service obligations. 

      Clearly, a swap will be required and the swap counterparty will need to be appropriately rated. The appropriate sovereign ceilings will also need to be taken into account.

      Additionally, all funds belonging to the Single Purpose Company will need to be segregated and held with appropriately rated banks. 

      There will need to be put in place a fairly substantial and sophisticated cash management regime to ensure that all payments are made by or on behalf of the Single Purpose Company on a timely basis (for details see point 7 below).
       

    5. Back-stopping package: adequate insurance including business interruption coverage and loss of potential income, monoline insurance guarantying the Single Purpose Company´s ability in meeting its obligations 

    6. Factoring the receivables is a form of insurance as well as over-collateralization i.e. when a larger portion of the assets over-collateralize a lesser amount.

      Certain standby financial commitments of the sponsors in the form of equity or quasi-equity contributions are also common. It would be also advisable to limit the distribution of dividends by the sponsors as well as limiting the transferability of the shares they own in the Single Purpose Company.
       

    7. Sovereign guarantee of the offtaker´s performance when the offtaker is a government-owned entity.

    8.  
    9. Escrow or Trust Accounts to ensure that the revenue generated by the project is properly collected and timely allocated to relevant items of cost and debt service, including debt service reserve accounts for future debt service payments.

    10. More specifically, the aim is to prevent the liquidity and reinvestment risks.

      The liquidity risk equates to the risk not that amounts are not received at all, but that they are received late such that the Single Purpose Company cannot pay in a timely fashion on a coupon date. 

      This risk can be addressed by the provision of a liquidity facility by an appropriately rated third party, or by building into the cash flows a spread/debt reserve account to be credited and replenished (where necessary) over time so as to ensure that a coupon payment can always be made.

      The reinvestment risk can be categorized as the inverse of liquidity risk. It occurs in the situation where, for example, the payments in respect of project income are received early such that the Single Purpose Company might have insufficient moneys to pay on the coupon date. 

      The solution to this problem is to ensure that the Single Purpose Company has available to it eligible investment criteria and/or a guaranteed investment contract under which it can invest funds for a guaranteed return. This may also be the solution to stage payment related issues where a note issue is launched to finance the project´s construction.

      In Toll highways, there is a problem in the cession of the right to collect the tolls since this is a cash flow that is not determined or determinable as required by the Spanish Civil Code for the cession of financial claims. A solution for the bank is to mortgage the highway.


    Financial design of the operation.

    Back to Index

    1. External Financing.

    Back to Index

    The external financing of the project varies from 50 % to 85 % obtained under different forms:

    • Senior Debt i.e. debt that has priority of claims ahead of other obligations. The syndication procedures might apply.
    • Normal Debt i.e. its position for eventual repayment in the event of bankruptcy follows that of senior debt, but precedes any repayment to the shareholders.
    • Leasing and/or Bonds but they are not very common since they are not compatible with the Senior Debt. 
    Besides that, bonds are complicated to use during the construction period of a turnkey project. A turnkey project will require advances of funding on a number of "milestone" dates. Therefore, it will be necessary to allow the issuance of bonds on this number of dates throughout construction (a cash collateral arrangement where the unutilized portion of the original issuance proceeds are deposited in a blocked account until required to be advanced would be easier). 


    2. Equity Commitment of the Sponsors.

    Back to Index

      It finances what is not covered by external financing i.e. from 15 % to 50 %.

      It consists in purchase of stocks in the Single Purpose Company. It must be pointed out that the subordinated debt guaranteed by the shareholders is considered as equity commitment.

    3. The inherent conflict between the sponsors AND the external financiers.

    Back to Index

    Typically, the debt provider is viewed as having a fixed or certain claim on a borrower's assets while the equity provider has a residual claim. Lenders will receive interest and principal payments in priority to equity distributions and will have priority in the event of liquidation. However, the lenders will have no voting rights and no right to participate in profits.

    In project financing however, the financiers' claim may appear to be as residual as that of the project sponsor. This is emphasized by the high gearing and long-term commitment expected from project financiers. Examples of areas that create conflicts for sponsors and financiers in a project financing are the level of return on debt funding and the extent of security taken.

    Return.

    Back to Index

      Despite the risks that a project financier takes, the return that it receives (while higher than on a full recourse loan) is likely to still reflect the assumption of debt rather than equity risks. Aside from the risks the financier will also want to reflect in its return the substantial time required to analyze, negotiate and administer this type of funding. 

      If the financier demands returns equivalent to an equity provider the project sponsor may prefer to find equity investors instead. The project sponsor may perceive equity investment as an advantage once returns demanded exceed a certain level as debt providers are often seen as less likely to share an entrepreneurial attitude providing a greater level of restrictions on the flexibility of the project.

    Security.

    Back to Index

    Granting security has a cost to the borrower. In addition to transactional costs there is the impact of the security on the credit of the borrower and, potentially, the project sponsor if security is required from it during the full recourse phase. 

    On the other hand, particularly in a situation where the borrower may be a shell company and the lender's recourse is limited to the assets of the project, security over and restrictions on the use of those assets, including the contractual arrangements on which it is relying for its cash flow, will be seen as important to the lender. 

    Security not only allows the lender to more readily control, operate or realize assets on default and to have a claim in priority to other creditors, but constrains the borrower's ability to dispose of assets, assume more debt and to terminate or alter any contractual arrangements on which the borrower (and the lenders) may be relying for cash flow or protection.

    However, the reality of security in a project finance is that it is often primarily defensive as the most likely circumstance in which a default under a project financing occurs (for example a failure of the technology being utilized) may mean that a realization of the secured assets is not possible.

    The tension arises between the financiers' desire to protect itself against all eventualities by restricting the borrower and the sponsor 's desire for flexibility to deal with unforeseen events.
     

    4. Allocating risk between the project sponsors AND the financiers.

    Back to Index

    It is essential to identify all conceivable risks in relation to the project from the outset, to provide protection against such of these risks as it is feasible to obtain protection and to allocate responsibility for any residual risk.

    The way in which the risks of a project are allocated amongst the parties to the project will impact on the total project cost.

    Project cost benefits can be realized when risk allocation is tailored to the circumstances of an individual project. Owners who routinely force maximum assumption of risk on the contractor are likely to incur higher project costs. Contract preparation that allocates risk with a balanced input from all parties will be the most cost effective. 

    The tension arises between the external financiers' desire to ensure that any residual risk to them is minimized by ensuring every conceivable event is identified and to the greatest extent possible, covered, including by contractual obligations (such as insurance), and the sponsor's desire to minimize the cost of the project. 

    This may mean that the more remote risks may be left uncovered (for instance where the cost of insuring a particular event is substantial and that event is wholly or partly "self insured" by the borrower) with the consequence that either of the financiers or, in certain cases, the sponsors bear that risk.

    Arguably, the most effective method of allocating risk will be to ensure that the party best equipped to manage and minimize a particular risk is the party to whom that risk is allocated. By properly allocating risks the parties should reduce the overall costs of those risks and should promote a better working relationship between themselves.
     

    REFERENCES.

    Back to Index

    • Risks in Projects; Instituto Tecnológico Autónomo de México (ITAM), Mexico, 1998.
    • Project Finance - Identifying and Allocating Risks; Russell McVeagh McKenzie Bartleet & Co, Wellington, New Zealand, 1998.
    • Problems and Solutions to Energy Efficiency Investment in Central Europe; EBRD , London, 1998.
    • Securitization in the Project Finance Sector; Norton Rose, London, 1997.
    • Today´s Business: Project Finance; Price Waterhouse, Toronto, 1997.
    • Guide to Energy Efficiency Bankable Proposals; European Commission, Directorate General for Energy, Brussels, 1997.
    • Los por qué y para qué de un Project Finance; Instituto de Empresa, Colegio de Dirección, Madrid, 1996.
    • Why Project Finance can make sense; Kelley Drye & Warren LLP, Los Angeles, 1996.
    • International Project Finance, Private Infrastructure Projects in Emerging Nations; Kelley Drye & Warren LLP, Los Angeles, 1994.
    • LBO Market Presentation; Banca Commerciale Italiana, New York, 1989.
     Back to Index

     

       HOME  |  CONTACT  |  SITEMAP  |  F.A.Qs.
    © Eurolibor.com   
    Jan. 2005